Question: Construct the project activity network using AON methodology. Activity Duration Predecessors A B C 35735425 DEFGH 3 | < 15 A A B, C B

Construct the project activity network using AON methodology.Activity Duration Predecessors A B C 35735425 DEFGH 3 | < 15A A B, C B D C E, F, G Activity Duration

Activity Duration Predecessors A B C 35735425 DEFGH 3 | < 15 A A B, C B D C E, F, G Activity Duration ES EF LS 357 35 425 ABCDE F G H 0 3 5 3 8 SOS LF Slack 0 3 | 5 10 2 7 3 10 3 10 10 13 10 13 8 13 12 17 13 17 13 17 10 12 15 17 17 22 17 22 | 5 | 4