Question: 1. A project network is given by the following table. Draw the network and show all path lengths. The minimum time required to complete the

1. A project network is given by the following table. Draw the network and show all path lengths. The minimum time required to complete the project is: Immediate Predecessors Activity Time ES LS EF LF slack Activity A B D E F G A B A A BC A DE D, F 5 days 10 days 9 days 7 days 4 days 3 days 3 days D E F G