Question: An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40,

An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40, EF C = 42, LF B =50, LF C = 57; activity times are A = 4, B = 6, C = 8 a 39 Ob Insufficient information Oc42 O d. 40 O e. 44