Question: An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40,
An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40, EF C = 42, LF B =49, LF C = 58; activity times are A = 4, B = 6, C = 8 a. 41 b. 39 c. Insufficient information d. 43 e. 38
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
