Question: An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40,
An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40, EF C = 42, LF B =49, LF C = 60; activity times are A = 4, B = 6, C = 8
Select one:
a. 34
b. Insufficient information
c. 39
d. 43
e. 30