Question: A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Preceding Optimistic Time Probable Time Pessimistic Time Expected
A partially solved PERT problem is detailed in the table below. Times are given in weeks.
| Activity | Preceding | Optimistic Time | Probable Time | Pessimistic Time | Expected Time | Variance |
| A | -- | 7 | 10 | 19 | ||
| B | A | 2 | 2 | 8 | ||
| C | A | 8 | 12 | 16 | ||
| D | A | 3 | 5 | 10 | ||
| E | B | 4 | 6 | 8 | ||
| F | B | 6 | 8 | 10 | ||
| G | C, F | 2 | 3 | 4 | ||
| H | D | 2 | 2 | 8 | ||
| I | H | 6 | 8 | 16 | ||
| J | G, I | 4 | 6 | 14 | ||
| K | E, J | 2 | 5 | 8 |
What is the probability of completion of the project before week 42?