Question: A PERT problem is detailed in the table below. Times are given in weeks. Activity Preceding Optimistic Time Probable Time/ Most likely time Pessimistic Time
A PERT problem is detailed in the table below. Times are given in weeks.
| Activity | Preceding | Optimistic Time | Probable Time/ Most likely time | Pessimistic Time |
| A | -- | 7 | 9 | 14 |
| B | A | 2 | 2 | 8 |
| C | A | 8 | 12 | 16 |
| D | A | 3 | 5 | 10 |
| E | B | 4 | 6 | 8 |
| F | B | 6 | 8 | 10 |
| G | C, F | 2 | 3 | 4 |
| H | D | 2 | 2 | 8 |
| I | H | 6 | 8 | 16 |
| J | G, I | 4 | 6 | 14 |
| K | E, J | 2 | 2 | 5 |
- Calculate the expected time and ES, EF, LF, and LS of each activity.
- Draw diagram network for this project.
- What are the project variance and the project standard deviation?
- What is the estimated completion time?
- What is the probability of completion of the project after week 40?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock