Question: A PERT problem is detailed in the table below. Times are given in weeks. Activity Preceding Optimistic Time Probable Time/ Most likely time Pessimistic Time

A PERT problem is detailed in the table below. Times are given in weeks.

Activity

Preceding

Optimistic

Time

Probable

Time/ Most likely time

Pessimistic

Time

A

--

7

9

14

B

A

2

2

8

C

A

8

12

16

D

A

3

5

10

E

B

4

6

8

F

B

6

8

10

G

C, F

2

3

4

H

D

2

2

8

I

H

6

8

16

J

G, I

4

6

14

K

E, J

2

2

5

  1. Calculate the expected time and ES, EF, LF, and LS of each activity.
  2. Draw diagram network for this project.
  3. What are the project variance and the project standard deviation?
  4. What is the estimated completion time?
  5. What is the probability of completion of the project after week 40?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!