Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 2 B 9

A project for improving a billing process has theA project for improving a billing process has the

A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 2 B 9 C 8 A D 11 10 B, C B F 4 D W UI 8 E 6 F, G b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Slack (weeks) A 2 B 9 8 D 11 E 10 F G 8 H 6