Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time(weeks) Immediate Predecessor(s) A 5 B 10 C
A project for improving a billing process has the following precedence relationships and activity times:
| Activity | Activity Time(weeks) | Immediate Predecessor(s) |
| A | 5 | |
| B | 10 | |
| C | 8 | A |
| D | 14 | B, C |
| E | 11 | B |
| F | 5 | D |
| G | 8 | E |
| H | 9 | F, G |
Calculate the slack for each activity. Which activities are on the critical path?
| Activity | Activity Time (weeks) | On criticalpath? | Slack (weeks) |
| A | 5 | No Yes | enter your response here |
| B | 10 | Yes No | enter your response here |
| C | 8 | No Yes | enter your response here |
| D | 14 | No Yes | enter your response here |
| E | 11 | No Yes | enter your response here |
| F | 5 | No Yes | enter your response here |
| G | 8 | No Yes | enter your response here |
| H | 9 | Yes No | enter your response here |