Question: A project for improving a billing process has the following precedence relationships and activity times: table [ [ Activity , Activity Time ( weeks

A project for improving a billing process has the following precedence relationships and activity times:
\table[[Activity,Activity Time (weeks),Immediate Predecessor(s)],[A,4,-],[B,12,-],[C,5,A],[D,12,B, C],[E,10,B],[F,5,D],[G,8,E],[H,9,F, G]]
a. Choose the correct network diagram below.
A. B.
c.
D.
A project for improving a billing process has the