Question: A project has 75 activities but we have only a partial information as shown below: activity =H, duration =20 days, IP= not given activity =N,

A project has 75 activities but we have only a
A project has 75 activities but we have only a partial information as shown below: activity =H, duration =20 days, IP= not given activity =N, duration =33 days,IP= not given activity =R, duration =22 days, IP= not given activity =K, duration =48 days, IP=H,N activity =P, duration =46 days, IP=H,N activity =C, duration =51 days, IP=R If LF(K)=125,LF(P)=139 and LF(C)=144, find the value of LS(N)