Question: A project has 75 activities but we have only a partial information as shown below: activity =H, duration =27 days, IP= not given activity =N,

A project has 75 activities but we have only a
A project has 75 activities but we have only a partial information as shown below: activity =H, duration =27 days, IP= not given activity =N, duration =19 days, IP= not given activity =R, duration =13 days, IP= not given activity =K, duration =31 days, IP=H,N activity =P, duration =33 days, IP=H,N activity =C, duration =36 days, IP=R If ES(H)=36,ES(N)=54 and ES(R)=51, find the value of EF(P)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!