Question: A project has 75 activities but we have only a partial information as shown below: activity =H, duration =13 days, IP= not given activity =N,

A project has 75 activities but we have only a
A project has 75 activities but we have only a partial information as shown below: activity =H, duration =13 days, IP= not given activity =N, duration =20 days, IP= not given activity =R, duration =25 days, IP= not given activity =K, duration =53 days, IP=H,N activity =P, duration =49 days, IP=H,N activity =C, duration =56 days, IP=R If LF(K)=178,LF(P)=140 and LF(C)=116, find the value of LS(N)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!