Question: A project has 75 activities but we have only a partial information as shown below: activity =F, duration =44 days,IP= not given activity =K, duration

A project has 75 activities but we have only a
A project has 75 activities but we have only a partial information as shown below: activity =F, duration =44 days,IP= not given activity =K, duration =45 days, IP= not given activity =P, duration =50 days,IP= not given activity =C, duration =43 days, P= not given activity =A, duration =19 days, IP=F,K activity =L, duration =18 days, P=K,P activity =Q, duration =28 days, IP=P activity =B, duration =17 days, IP=P,C If ES(F)=75,ES(K)=81,ES(P)=63 and ES(C)=79, find the value of EF(L)