Question: A project has 75 activities but we have only a partial information as shown below: activity =F, duration =56 days,IP= not given activity =K, duration

A project has 75 activities but we have only a
A project has 75 activities but we have only a partial information as shown below: activity =F, duration =56 days,IP= not given activity =K, duration =52 days, IP= not given activity =P, duration =57 days,IP= not given activity =C, duration =42 days, IP= not given activity =A, duration =24 days, IP=F,K activity =L, duration =40 days, IP=K,P activity =Q, duration =31 days, IP=P activity =B, duration =19 days, P=P,C If LF(A)=192,LF(L)=164,LF(Q)=151 and LF(B)=145, find the value of LS(P)