Question: A project has 75 activities but we have only a partial information as shown below: activity =H, duration =17 days, IP= not given activity =N,

A project has 75 activities but we have only a
A project has 75 activities but we have only a partial information as shown below: activity =H, duration =17 days, IP= not given activity =N, duration =19 days, IP= not given activity =R, duration =30 days, IP= not given activity =K, duration =50 days, P=H,N activity =P, duration =44 days, IP=H,N activity =C, duration =35 days, P=R If ES(H)=52,ES(N)=51 and ES(R)=39, find the value of EF(K)