Question: A project has 75 activities but we have only a partial information as shown below: activity =H, duration =21 days, IP= not given activity =N,

A project has 75 activities but we have only a
A project has 75 activities but we have only a partial information as shown below: activity =H, duration =21 days, IP= not given activity =N, duration =30 days,IP= not given activity =R, duration =17 days, IP= not given activity =K, duration =44 days, IP=H,N activity =P, duration =41 days, IP=H,N activity =C, duration =38 days, IP=R If LF(K)=144,LF(P)=126 and LF(C)=174, find the value of LS(R)