Question: A project has 75 activities but we have only a partial information as shown below: activity =E, duration =21 days,IP= not given activity =K, duration

A project has 75 activities but we have only a
A project has 75 activities but we have only a partial information as shown below: activity =E, duration =21 days,IP= not given activity =K, duration =49 days, IP= not given activity =P, duration =46 days, IP=E activity =A, duration =41 days, IP=E activity =L, duration =54 days, IP=K,P activity =R, duration =78 days, IP=P,A activity =G, duration =78 days, IP=P,A If LF(L)=257,LF(R)=249 and LF(G)=234, then find the value of LS(P)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!