Question: , A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A 43 0.3 B E 40 1

, A project has five activities with the
, A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A 43 0.3 B E 40 1 D 15 0.34 22 3.36 End End 13 0 E What is the probability that the project will be completed within 88 days? a. 0 b. 0.18 C. 0.82 d. 0.25 e. 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!