Question: A project network is shown below. Use a forward and a backward pass to determine the critical path, also fill out the table below for
A project network is shown below. Use a forward and a backward pass to determine the critical path, also fill out the table below for precedence activities, slack and if an activity is on a critical path or
not. Activity times are in weeks. Show ES, LS, EF, and LF on the diagram itself.