Question: A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below.

A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below.

Activity

Precedence Activities

Activity

Time (weeks)

A

--

5

B

--

4

C

--

8

D

A, B

4

E

C

12

F

C

10

G

D, E

3

H

E

2

I

E, F

5

  • What is the completion time of this project?

25 days

24 weeks

25 weeks

27 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!