Question: A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below.
A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below.
|
Activity | Precedence Activities | Activity Time (weeks) |
| A | -- | 5 |
| B | -- | 4 |
| C | -- | 8 |
| D | A, B | 4 |
| E | C | 12 |
| F | C | 10 |
| G | D, E | 3 |
| H | E | 2 |
| I | E, F | 5 |
- What is the completion time of this project?
| 25 days | ||
| 24 weeks | ||
| 25 weeks | ||
| 27 weeks |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
