Question: Activity D on a CPM network has predecessors B and C , and has successor F . D has quration 6 . B ' s
Activity D on a CPM network has predecessors B and C and has successor F D has quration Bs earliest finish is while Cs is Fs late start is Which of the following is true?
Select the correct response:
All of the above are true
C is completec before B
B is a critical activity
D is critical, and has zero slack
has no slack but is not critical.