Question: Activity D on a CPM network has predecessors B and C , and has successor F . D has quration 6 . B ' s

Activity D on a CPM network has predecessors B and C, and has successor F. D has quration 6. B's earliest finish is 18, while C's is 20. F's late start is 26. Which of the following is true?
Select the correct response:
All of the above are true
C is completec before B.
B is a critical activity
D is critical, and has zero slack
has no slack but is not critical.
 Activity D on a CPM network has predecessors B and C,