Question: Activity Immediate Predecessors Completion Time (Weeks) A N/A 4 B A 5 C B 2 D B 4 E B 3 F E 3 G
Activity Immediate Predecessors Completion Time (Weeks) A N/A 4 B A 5 C B 2 D B 4 E B 3 F E 3 G A 1 H F 6 I C,D,G 5 J A 12 2. What are the earliest start and the earliest finish of the activity I? (C) a. 11,16 b. 5,10 c. 13,18 d. 16,21