Question: Activity Preceding Optimistic Time Probable Time/ Most likely time Pessimistic Time A -- 7 9 14 B A 2 2 8 C A 8 12
| Activity | Preceding | Optimistic Time | Probable Time/ Most likely time | Pessimistic Time |
| A | -- | 7 | 9 | 14 |
| B | A | 2 | 2 | 8 |
| C | A | 8 | 12 | 16 |
| D | A | 3 | 5 | 10 |
| E | B | 4 | 6 | 8 |
| F | B | 6 | 8 | 10 |
| G | C, F | 2 | 3 | 4 |
| H | D | 2 | 2 | 8 |
| I | H | 6 | 8 | 16 |
| J | G, I | 4 | 6 | 14 |
| K | E, J | 2 | 2 | 5
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts