Question: Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node, along with the
Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node, along with the critical path.
Activity Predecessor Duration (days)
A NONE 1
B A 2
C NONE 1
D NONE 1
E C 3
F D 2
G B, E 3
H F 2
I G, H 1
J F 4
K I 4
L J 3
M J 3
N L, M 2