Question: Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node, along with the

Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node, along with the critical path.

Activity Predecessor Duration (days)

A NONE 1

B A 2

C NONE 1

D NONE 1

E C 3

F D 2

G B, E 3

H F 2

I G, H 1

J F 4

K I 4

L J 3

M J 3

N L, M 2