Question: Activity Predecessor Duration (weeks) TA 5 B 8 IC A 6 D . 3 E B 4 F DE 3 G C 2 a. Draw

Activity Predecessor Duration (weeks) TA 5 B 8 IC

Activity Predecessor Duration (weeks) TA 5 B 8 IC A 6 D . 3 E B 4 F DE 3 G C 2 a. Draw the network diagram. b. Find and list the ES, EF, LS, and LF. C. What is the critical path? What is the duration of the project? d. Find and list the Total Float and Free Float for each activity