Question: Activity Predecessors Durations (days) A none 2 B A 3 A B 1 E B and C 3 D and E 6 G C and

Activity Predecessors Durations (days) A none 2 B

Activity Predecessors Durations (days) A none 2 B A 3 A B 1 E B and C 3 D and E 6 G C and D 3 For the preceding project, the slack for activity B is: Select one: a. 5 b. 2 C. 3 d. 1