Question: Activity time estimates for a production line design & implementation project at the CBA factory are as follows: Activity Time (in days) Immediate predecessors A
Activity time estimates for a production line design & implementation project at the CBA factory are as follows:
| Activity | Time (in days) | Immediate predecessors |
| A | 60 | --- |
| B | 72 | --- |
| C | 50 | A |
| D | 60 | B, C |
| E | 45 | B, C |
| F | 77 | D |
| G | 40 | E, F |
Find early start, early finish, late start, and late finish times for every activity.