Question: An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40,
An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40, EF C = 42, LF B =44, LF C = 50; activity times are A = 4, B = 6, C = 8
a. 30
b. 38
c. Insufficient information
d. 34
e. 34