Question: As implied by the network, tasks A and B can be done independently of tasks C and D . But B cannot start until A
As implied by the network, tasks A and B can be done independently of tasks C and D But B
cannot start until A is done, and D cannot start until C is done. This is called a finishtostart
task dependency, by far the most common type. Starttostart,finishtofinish, etc. also exist
and can be specified in Microsoft Project
Time required to do each task is uncertain. Very often, the triangular distribution is used to
estimate the duration of a task. The minimum is everything went right heh heh the mode is
the most likely duration, and the maximum is lots of things went wrong. Assume the
following: