Question: As implied by the network, tasks A and B can be done independently of tasks C and D . But B cannot start until A

As implied by the network, tasks A and B can be done independently of tasks C and D. But B
cannot start until A is done, and D cannot start until C is done. (This is called a finish-to-start
task dependency, by far the most common type. Start-to-start,finish-to-finish, etc. also exist
and can be specified in Microsoft Project).
Time required to do each task is uncertain. Very often, the triangular distribution is used to
estimate the duration of a task. The minimum is everything went right [heh heh], the mode is
the most likely duration, and the maximum is lots of things went wrong. Assume the
following:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!