Question: Consider the following work breakdown structure: Activity Predecessors Expected Duration A Start 50 B Start 111 C Start 100 D A 25 E B 100
Consider the following work breakdown structure:
| Activity | Predecessors | Expected Duration |
| A | Start | 50 |
| B | Start | 111 |
| C | Start | 100 |
| D | A | 25 |
| E | B | 100 |
| F | D | 65 |
What is the Latest Finishing Time for Activity F?