Question: Consider the following work breakdown structure: Duration Estimates (Days) Activity Precedes Most Likely Start U,V w W.X Pessimistic What is the estimated expected ( mean)

Consider the following work breakdown structure:

Consider the following work breakdown structure: Duration Estimates (Days) Activity Precedes Most Likely Start U,V w W.X Pessimistic What is the estimated expected ( mean) time for activity Y? 38 days 26 days 35 days 30 days