Question: Consider the following work breakdown structure: table [ [ , Start,Finish,Duration ( days ) ] , [ Activity , Node,Node,Optimistic,Most Likely,Pessimistic ] , [
Consider the following work breakdown structure:
tableStart,Finish,Duration daysActivityNode,Node,Optimistic,Most Likely,PessimisticABCD
What is the estimated expected mean time for project completion?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
