Question: Consider the following work breakdown structure: table [ [ , Start,Finish,Duration ( days ) ] , [ Activity , Node,Node,Optimistic,Most Likely,Pessimistic ] , [

Consider the following work breakdown structure:
\table[[,Start,Finish,Duration (days)],[Activity,Node,Node,Optimistic,Most Likely,Pessimistic],[A,1,2,41,50,59],[B,1,3,54,60,66],[C,2,4,58,70,82],[D,3,4,32,41,44]]
What is the estimated expected (mean) time for project completion?
 Consider the following work breakdown structure: \table[[,Start,Finish,Duration (days)],[Activity,Node,Node,Optimistic,Most Likely,Pessimistic],[A,1,2,41,50,59],[B,1,3,54,60,66],[C,2,4,58,70,82],[D,3,4,32,41,44]] What is