Question: For a project, the following earned value data have been assessed: AC: $ 4,000,000 CV: $ -500,000 SPI: 1.12 BaC: $ 9,650,000 What is the
For a project, the following earned value data have been assessed: AC: $ 4,000,000 CV: $ -500,000 SPI: 1.12 BaC: $ 9,650,000 What is the earned value of the project? Select one: a. $4,480,000 b. $5,650,000 c. $3,000,000 d. $3,500,000