Question: For a project, the following earned value data have been assessed: AC: $ 4,000,000 CV: $ -600,000 SPI: 1.12 BaC: $ 9,650,000 What is the
- For a project, the following earned value data have been assessed:
- AC: $ 4,000,000
- CV: $ -600,000
- SPI: 1.12
- BaC: $ 9,650,000
What is the earned value of the project?
Group of answer choices
$5,650,000
$3,400,000
$3,000,000
2. In a project, a cost incentive contract has been awarded to a contractor with the following parameters: What is the point of total assumption (PTA, breakpoint) of the project? Hint: PTA Formula.
- Target Cost 180,000
- Target Fee 30,000
- Target Price 280,000
- Sharing Ratio (Cost Overrun Sharing Ratio) 60/40
- Ceiling Price 300,000
Group of answer choices
$213,334
$195,852
$205,655
$250,340