Question: Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations

Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 32 and a Path Standard Deviation = 5. For Path 1-3-4-5 we have a Path Mean = 30 and a Path Standard Deviation = 2. Determine both the Probability that Path 1-2-5 will finish in 32 Days or Less and the Probability that the Project will finish in 32 Days or Less.
Question 3 options:
|
| 0.84134474 : 0.841148982 |
|
| 0.5 : 0.42067237 |
|
| 0.788144666 : 0.787080697 |
|
| 0.884930268 : 0.884902228 |