Question: Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations
Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 34 and a Path Standard Deviation = 2. For Path 1-3-4-5 we have a Path Mean = 32 and a Path Standard Deviation = 4. Determine both the Probability that Path 1-2-5 will finish in 34 Days or Less and the Probability that the Project will finish in 34 Days or Less.
Question 3 options:
|
| 0.5 : 0.345731234 |
|
| 0.84134474 : 0.707860972 |
|
| 0.933192771 : 0.834601105 |
|
| 0.933192771 : 0.834601105 |