Question: QUESTION 1 Given is a CPM project network diagram as shown below. A F Start E End B D G B D Activity days Start

QUESTION 1 Given is a CPM project network diagram
QUESTION 1 Given is a CPM project network diagram as shown below. A F Start E End B D G B D Activity days Start 0 A 2 E 4 F 2 G 3 H 2 End 0 6 8 3 a) The Project Completion time days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity C - days. d) The critical activities are (ex. Fill in answer as: ABCD)