Question: Given is a PERT project network diagram as shown below. table [ [ Activity , Start,A , B , C , D , E

Given is a PERT project network diagram as shown below.
\table[[Activity,Start,A,B,C,D,E,F,G,H,End],[Time,0,2.61,5.00,6.31,5.31,2.65,4.23,4.12,7.13,0]]
a) The Project Completion time = Blank 1(in 2 decimal places) b) The Earliest Start time, ES, of Activity G=Blank 2(in 2 decimal places) c) The Latest Finish time, LF, of A citivity C= Blank 3(in 2 decmal places) d) The critical activities are = Blank 4(ex. type in critical activities as, ABCD, no comma, no space)
Blank 1 Addyout answer
Blank 2 Addyour answer
Blank 3 Addjour answe?
Blank 4 Add your answer
 Given is a PERT project network diagram as shown below. \table[[Activity,Start,A,B,C,D,E,F,G,H,End],[Time,0,2.61,5.00,6.31,5.31,2.65,4.23,4.12,7.13,0]]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!