Question: Given is a PERT project network diagram as shown below. a F Start E H End B D G Activity Start Time 0 D A

Given is a PERT project network diagram as shown
Given is a PERT project network diagram as shown below. a F Start E H End B D G Activity Start Time 0 D A 2.61 E B 5.00 F H End 6.31 5.31 G 4.12 2.65 4.23 7.13 0 a) The Project Completion time (in 2 decimal places) b) The Earliest Start time, ES, of Activity G (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C - (in 2 decimal places) d) The critical activities are (ex. type in critical activities as ABCD, no comma, no space)