Question: Given is a PERT project network diagram as shown below. A c Start E H End D G Activity Start Time B JA 1:52 C

Given is a PERT project network diagram as shown
Given is a PERT project network diagram as shown below. A c Start E H End D G Activity Start Time B JA 1:52 C 7.02 End 36 3.69 1.28 4.36 G 16:24 3.25 10 a) The Project Completion time - (in 2 decimal places b) The Earliest Start time, ES, of Activity G - (in 2 decimal places c) The Latest Finish time, LF of Acitivity C in 2 decimal places) d) The critical activities are (ex. type in critical activities - ABCD no comma, no space)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!