Question: Given is a PERT project network diagram as shown below. Activity Start A B C D E F G H End Time 0 2.17 3.38
-
Given is a PERT project network diagram as shown below.
Activity
Start
A
B
C
D
E
F
G
H
End
Time
0
2.17
3.38
1.89
3.15
2.68
6.14
3.12
3.16
0
a) The Project Completion time = Blank 1 (in 2 decimal places) b) The Earliest Start time, ES, of Activity G = Blank 2 (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C = Blank 3 (in 2 decimal places) d) The critical activities are = Blank 4 (ex. type in critical activities as ABCD, no comma, no space)
- Blank 1
- Blank 2
- Blank 3
- Blank 4
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
