Question: Given is a PERT project network diagram as shown below. Activity Start A B C D E F G H End Time 0 2.17 3.38

  1. Given is a PERT project network diagram as shown below.

    Activity

    Start

    A

    B

    C

    D

    E

    F

    G

    H

    End

    Time

    0

    2.17

    3.38

    1.89

    3.15

    2.68

    6.14

    3.12

    3.16

    0

    a) The Project Completion time = Blank 1 (in 2 decimal places) b) The Earliest Start time, ES, of Activity G = Blank 2 (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C = Blank 3 (in 2 decimal places) d) The critical activities are = Blank 4 (ex. type in critical activities as ABCD, no comma, no space)