Question: Given is a PERT project network diagram as shown below. Activity Start A B C D E F G H End Time 0 2.36 1.36

Given is a PERT project network diagram as shown below.

Activity

Start

A

B

C

D

E

F

G

H

End

Time

0

2.36

1.36

4.32

7.12

1.36

8.42

2.36

4.65

0

a) The Project Completion time = Blank 1 (in 2 decimal places) b) The Earliest Start time, ES, of Activity G = Blank 2 (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C = Blank 3 (in 2 decimal places) d) The critical activities are = Blank 4(ex. type in critical activities as ABCD, no comma, no space)