Question: Given is a PERT project network diagram as shown below. Activity Start A B C D E F G H End Time 0 2.36 1.36
Given is a PERT project network diagram as shown below.
| Activity | Start | A | B | C | D | E | F | G | H | End |
| Time | 0 | 2.36 | 1.36 | 4.32 | 7.12 | 1.36 | 8.42 | 2.36 | 4.65 | 0 |
a) The Project Completion time = Blank 1 (in 2 decimal places) b) The Earliest Start time, ES, of Activity G = Blank 2 (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C = Blank 3 (in 2 decimal places) d) The critical activities are = Blank 4(ex. type in critical activities as ABCD, no comma, no space)