Question: In a simple CPM Project network, three tasks A , B and C must be completed. A must be completed before B and B must

In a simple CPM Project network, three tasks A, B and C must be completed. A must be completed before B and B must be completed before beginning task C. A's single task time estimate =5;B' s single task time estimate =10;C' s single task time estimate =7. Which of the following statements is true?
The critical path is B-C.
The critical path is A-B-C.
The critical path is A-C.
The critical path is C-B-A.
 In a simple CPM Project network, three tasks A, B and

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!