Question: In a simple CPM Project network, three tasks A , B and C must be completed. A must be completed before B and B must
In a simple CPM Project network, three tasks A B and C must be completed. A must be completed before and must be completed before beginning task As single task time estimate ; s single task time estimate ; s single task time estimate Which of the following statements is true?
The critical path is BC
The critical path is ABC
The critical path is AC
The critical path is