Question: Need Help, thanks. In a simple CPM Project network, three tasks A,B and C must be completed. A and B have no predecessors, and both
Need Help, thanks.

In a simple CPM Project network, three tasks A,B and C must be completed. A and B have no predecessors, and both A and B must be completed before beginning task C. A's single task time estimate =5; B's single task time estimate =10; C single task time estimate =7. Which of the following statements is true? The latest finish time for C is 12. The latest start time for A is 5. The latest start time for C is 12. The latest finish time for A is 11
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
