Question: In a simple CPM Project network, three tasks A,B and C must be completed. A and B have no predecessors, and both A and B

In a simple CPM Project network, three tasks A,B and C must be completed. A and B have no predecessors, and both A and B must be completed before beginning task C. A's single task time estimate =5; B's single task time estimate =10; C's single task time estimate =7. Which of the following statements is true? The earliest finish time for C is 10. The earliest start time for C is 10 . The earliest finish time for A is 10 . The earliest start time for A is 10