Question: In a simple CPM Project network, three tasks A, B and C must be completed. A and B have no predecessors, and both A and
In a simple CPM Project network, three tasks A, B and C must be completed. A and B have no predecessors, and both A and B must be completed before beginning task C. As single task time estimate = 5; Bs single task time estimate = 10; Cs single task time estimate = 7. Which of the following statements is true? A. The earliest start time for A is 10. B. The earliest finish time for A is 10. C. The earliest finish time for C is 10. D. The earliest start time for C is 10.