Question: In a simple PM Project network, three tasks A , B and C must be completed. A must be completed before B and B must

In a simple PM Project network, three tasks A, B and C must be completed. A must be completed before B and B must becompleted before beginning task C. A's single task time estimate =5; B's single task time estimate =10; C's single task time estimate=7. Which of the following statements is true?O The critical path is B-C. The critical path is C-B-A. The critical path is A-B-C.O The critical path is A-C.