Question: In a simple PM Project network, three tasks A , B and C must be completed. A must be completed before B and B must
In a simple PM Project network, three tasks A B and C must be completed. A must be completed before B and B must becompleted before beginning task C As single task time estimate ; Bs single task time estimate ; Cs single task time estimate Which of the following statements is true? The project completion time is The project completion time is The project completion time is normally distributed.O The project completion time is
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
