Question: In a simple PM Project network, three tasks A , B and C must be completed. A must be completed before B and B must

In a simple PM Project network, three tasks A, B and C must be completed. A must be completed before B and B must becompleted before beginning task C. A's single task time estimate =5; B's single task time estimate =10; C's single task time estimate=7. Which of the following statements is true? The project completion time is 17. The project completion time is 12. The project completion time is normally distributed.O The project completion time is 22.