Question: Need urgent help!! The activity table is given below. Activity Predecessor Duration ES LF 0 1 Clear site 3 0 3 1 2 Survey and
Need urgent help!!
The activity table is given below.
| Activity | Predecessor | Duration | ES | LF |
| 0 1 | Clear site | 3 | 0 | 3 |
| 1 2 | Survey and layout | 2 | 3 | 5 |
| 2 3 | Rough grade | 2 | 5 | 7 |
| 3 4 | Drill wel | 15 | 7 | 22 |
| 3 - 6 | Water tank foundations | 4 | 7 | 12 |
| 3 9 | Excavate sewer | 10 | 7 | 21 |
| 3 10 | Excavate electrical manholes | 1 | 7 | 21 |
| 3 12 | Pole line | 6 | 7 | 29 |
| 4 - 5 | Well pump | 2 | 22 | 24 |
- Draw the CPM network with path duration and determine the critical path
- Draw the CPM path with ES, EF, LS, LF and determine the critical path.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
